F10 – Notification of a Construction Project
Embarking on a medium/large scale construction project requires notification to HSE under Construction Design and Management (CDM) Regulation 2015, using a F10 form under the HSE website.
Who must notify HSE
If the client is a:
-
- commercial client, then they must notify HSE
- domestic client – notification must be carried out by the:
- contractor (or principal contractor if there is more than one contractor)
- principal designer where there is a written agreement that they will carry out the client’s duties
The F10 notification must include the details included in schedule 1 of the regulations:
-
-
- The date of forwarding the notice.
- The address of the construction site or precise description of its location.
- The name of the local authority where the is located.
- A brief description of the project and the construction work that it entails.
- The following contact details of the client: name, address, telephone number and (if available) an email address.
- The following contact details of the principal designer: name, address, telephone number and (if available) an email address.
- The following contact details of the principal contractor: name, address, telephone number and (if available) an email address.
- The date planned for the start of the construction phase.
- The time allocated by the client under regulation 4(1) for the construction work.
- The planned duration of the construction phase.
- The estimated maximum number of people at work on the construction site.
- The planned number of contractors on the construction site.
- The name and address of any contractor already appointed.
- The name and address of any designer already appointed.
- A declaration signed by or on behalf of the client that the client is aware of the client duties under these Regulations.
-
Link to the F10 notification form will be found here: